Structural design
Building physics

Regional Vocational Training Center (RBZ) in Kiel

Two buildings for school, teaching and administration

Facts and figures

Client:
PPP process, AMATIS Verwaltung GmbH, Pullach i. Isartal
Object:
Two 2-4 storey school, teaching and administration buildings for a total of approx. 2,400 pupils (RBZ I: GFA 7,800 m² / Building C: GFA approx. 7,000 m²) built in four construction phases
Design:
Zastrow + Zastrow, Kiel; AX5 Architects, Kiel
Services:
Structural design
Building physics
ENEV verification
Special features:
  • Connection to the existing building stock
  • Construction during ongoing school operations in confined spaces
  • Construction time: 14 months (RBZ I) and 12 months (Building C)
  • Use of semi-finished and fully finished parts
  • Increased energy standards
  • Basement as waterproof construction
  • Cantilevers of 3 storeys above the entrance area (Building C)